Question 1
A project __________ is the tangible end product that the project team must produce or deliver.
schedule
objective
budget
scope
Question 2
The collapse of a retaining wall could be a risk to the project __________ for a garden construction project.
payment
objective
budget
scope
Question 3
The project purpose should:
summarize the need and justification for the project.
state what is expected to be accomplished.
state the major end products or items expected to be produced.
be concise and create a vision for the end result of the project.
Question 4
Materials that would be used for a construction project are:
concrete truck delivery fees and permits.
people, money, and time.
lumber, windows, and paint.
rough carpenters, plumbers, and finishers.
Question 5
The __________ section of the project scope document is where the contractor or project team can state and clarify exactly what is included in the work scope and provide an opportunity to reconsider items that are not stated but that the customer may have forgotten to include in her requirements or RFP.
statement of work
customer requirement
deliverables
acceptance criteria
Question 6
When estimating the types and quantities of resources required for each specific activity, it is valuable to involve a person who:
is hired by the customer to be a consultant regardless of experience on the type of project.
has expertise or experience with the activity to help make the estimate.
has experience negotiating contracts.
has the most experience using a project management information system.
Question 7
Materials costs in the project costs estimate are the estimated costs of materials that the project team or contractor:
want to have in supply in the office.
needs even if not for this particular project.
needs to purchase for the project.
might want to use on the project.
Question 8
The __________ is the warning flag for when to implement the action plan for the risk.
action trigger
priority order
mitigation plan
degree of impact
Question 9
The project manager coordinates the activities of the __________ to ensure that they perform the right tasks at the proper time, as a cohesive group.
stakeholders
various team members
suppliers
project sponsor
Question 10
__________ body language can be a frown, crossed arms, slouching, fidgeting, gazing or looking away, doodling, or yawning.
Neutral
Negative
Critical
Positive